N52 Tullamore to Kilbeggan Link Scheme

Third Public Consultation – Emerging Preferred Route Corridor

17th September to 29th October 2021

The Project Team has undertaken an appraisal of the Route Corridor Options published in November 2020 and has considered feedback received through the second non-statutory Public Consultation to identify an ‘Emerging Preferred Route Corridor’. We now seek your feedback on this Emerging Preferred Route Corridor.

Following completion of the Stage 2 Project Appraisal process, a combination of Options 2 and 3 (referred to as Combination Option 2-3) was identified as the optimum Route Corridor Option, having regard to the overall benefits and impacts based on the six criteria to be considered for transport projects.

The Route Corridor is circa 8.1km in length and maximises the use of existing upgraded sections of the N52, i.e., the approach to the Tullamore Bypass at the south and the approach to the M6 Motorway junction at the north.

The route corridor follows the existing N52 until just north of the L2003 Ballynamona Road, where it diverges to the east. It crosses the L2005 and the L2006 High Road before merging back with the existing N52 again, north of the county boundary in the townland of Curraghglass.

View the Emerging Preferred Route Corridor map here.

Have your say:

During this Public Consultation, we want to hear your views on the Emerging Preferred Route Corridor. We welcome your feedback on any issues or information which you think should be considered in the identification of the Final Preferred Route.

In compliance with current COVID-19 measures, and to provide access to project information in a safe environment, an online consultation room is available at www.n52tullamoretokilbeggan.ie.

All project information, including an interactive map of the Emerging Preferred Route Corridor and the consultation questionnaire is available to view and submit online.

Download the Third Public Consultation Brochure here.

Download the Third Public Consultation Questionnaire here.

Complete the online Questionnaire here.

Manned in-person consultation days are arranged for Monday 20th September and Wednesday 29th September at the Tullamore Court Hotel, where interested parties will have an opportunity to discuss the scheme with the Project Team.

Attendance at these in-person consultation days is strictly by appointment only and will be limited to 2 persons per booking. Walk-ins will not be possible. Please visit the online booking system through the online consultation room, where a meeting slot can be booked with a member of the Project Team. Strict adherence to COVID-19 guidelines and social distancing will apply, and proof of vaccination may be requested.

During the 6-week consultation period, the Project Team are available for phone calls and follow-up online meetings as required.

Once you have reviewed the project information and Emerging Preferred Route Corridor map, please complete and return the consultation questionnaire to the Project Team.

All feedback should be returned to the Project Team by 29th October 2021.

How to return your completed questionnaire:

Online: Complete the Online Questionnaire

Email: info@n52tullamoretokilbeggan.ie

Post: N52 Tullamore to Kilbeggan Project Team, RPS, West Pier Business Campus, Dun Laoghaire, Co. Dublin. A96 N6T7

Phone: 01 5239274 (Weekdays 9am-5pm)

Please Visit the Virtual Consultation Room

Second Public Consultation – Route Corridor Options
6th November 2020 to 11th December 2020

Please note this phase of public consultation is now over.

The N52 Tullamore to Kilbeggan Link Scheme is now at the ‘Option Selection’ phase in accordance with the TII Project Management Guidelines.

Stage 1 of the Option Selection phase, which included a public consultation held from June-July 2020, identified constraints within the study area. The project team then used engineering, environmental and economic criteria to identify feasible Route Corridor Options for the N52 Tullamore to Kilbeggan Link Scheme.

Five Route Corridor Options have now been identified to proceed to Stage 2 of the Option Selection phase. View Route Corridor Options Map.

Have Your Say

During this consultation, we are inviting feedback on the Route Corridor Options that could inform the design of the project. We welcome your feedback on any issues or information, relating to the corridors, which you think should be considered by the project team in selecting a preferred route corridor.

In compliance with current COVID-19 measures, and to provide access to project information in a safe environment, an online consultation room is available here: Visit the Online Consultation Room

Once you have reviewed the project information and route corridor options map, please complete and return the consultation questionnaire to the project team.

All feedback should be returned to the project team by 11th December 2020.

Download the Second Public Consultation Brochure Here.

Download the Second Public Consultation Questionnaire Here.

How to return your completed questionnaire:

Online: Complete the Online Questionnaire.

Email: info@n52tullamoretokilbeggan.ie

Post: N52 Tullamore to Kilbeggan Project Team, RPS, West Pier Business Campus, Dun Laoghaire, Co. Dublin. A96 N6T7

Phone: 01 5239274 (Weekdays 9am-5pm)

Meet with the Project Team

The N52 project team is available to answer any questions and provide information to assist you with your submission.

The project team can be contacted during office hours at 01 5239274 (Weekdays 9am-5pm) and at info@n52tullamoretokilbeggan.ie.

If you would like to arrange an online consultation with a member of the project team, please contact us by phone, email, or via the online meeting booking facility. Online meetings will be facilitated during the week of 23rd November – 27th November.

Should the current COVID-19 restrictions be eased during the course of the public consultation period, it may be possible to facilitate ‘in-person’ meetings, by appointment only, at a suitable venue in Tullamore. Strict adherence to COVID-19 guidelines will apply, in order to safeguard the health and safety of the public and staff.

Visit the Virtual Consultation Room

First Public Consultation – Study Area and Constraints
15th June 2020 to 27th July 2020

Please note this phase of public consultation is now over.

Have Your Say!

We want to hear your views on the Study Area and Constraints to inform the design of the project. We are particularly interested to hear from local people and interested parties regarding any constraints or issues you may be aware of and which may or may not be in the public domain.

Tell us about anything else that you think should be considered by the engineers and environmental consultants whilst they are planning and designing the route.

Download the First Public Consultation Brochure Here

Download the First Public Consultation Questionnaire Here

Completed questionnaires (along with any other feedback) can be emailed to the project team at: info@n52tullamoretokilbeggan.ie

Alternatively you can post your completed questionnaire to us at:
N52 Tullamore to Kilbeggan Project Team,
RPS,
West Pier Business Campus,
Dun Laoghaire,
Co. Dublin.

Contact the project team by telephone at 01 5239274 (Monday to Friday)

All feedback should be returned to the project team by 27th July 2020.